5/28/24 @ 3:27 pm Memorial Storm Update

We are making great process today with the 77 line-workers we currently have out in the field. The estimated number of members out of power is 3,408. There is still work to be completed on three-phase lines and pole change outs that is going on today and hopefully will be wrapped up tomorrow. Those poles take 2-3 hours each to change. Once those poles have been changed out, crews will move to single phase lines. We do not have a timeline for individuals with line damage to their homes.

 

Fiber Update we were able to get to make some repairs today that restored most of the outage created from the cut mainline last night. Once electric is back up and repaired we will begin trouble shooting individual fiber outages.